To meet the government’s target (Net Zero), our industry must deliver more than 5 times the amount of electricity transmission infrastructure in the next 7 years, than has been built in the past 30 years.”
This is a phenomenal undertaking for National Grid, and it's going to take some time and resources to complete.
As of February 2023, the National Grid had a connections queue of 257MW worth of projects waiting to connect against a 147GW of low carbon requirement to achieve net zero. Unfortunately, only 30-40% of the applications in the queue materialise into an actual project. This has meant that new connections are being given a date of between 12-15years before they can connect, which are dates that are not acceptable to investors.
One cause for optimism is that the core players with the power to transform our grid infrastructure have all issued definitive indicators that there is appetite for reforms which will enable a stronger, more resilient, more flexible grid.
In order to try and free up capacity and remove the “speculative projects”, as of March 2023 the National Grid published a 5-point plan to help.
1) Operating a Transmission Entry Capacity Amnesty until April 2023, allowing developers to terminate their connection contracts without incurring liabilities, freeing up capacity in the queue.
2) Updating modelling assumptions to reflect current connection rates and reducing the assumption that most projects in the queue will connect.
3) Changing the treatment of storage, including batteries, on the network to allow them to connect faster and free up capacity for other projects.
4) Developing new contractual terms for connection contracts to manage the queue more efficiently so that those projects that are progressing can connect and those that are not can leave the queue.
5) A ‘soon-to-be-made’ offer of an interim option for storage projects to connect to the network sooner, but with the caveat that they may be required to turn off more frequently when the system is under stress without initially being paid to do so.
Additionally, OFGEM issued an open letter on future reforms to the electricity connections process, which focuses on reforms to deliver benefits to current and future customers, accelerate progress to net zero, begin to deliver as soon as possible, coordinate across onshore and offshore networks on the transmission and distribution grids and ensure the reforms are resilient to wider reforms.
In April 2023, the The Energy Networks Association (ENA) published a three-step plan to speed up connections to the grid. If successful, this will result in mature projects which are closer to delivery gaining priority. Another core priority is changing how transmission and distribution networks co-ordinate connections, improving their interactivity. The final of the three points aims to bring greater flexibility for storage customers through new contractual options.
A combination of the work being undertaken by National Grid, OFGEM and the ENA, alongside the new investment in the Grid infrastructure should enable projects to connect earlier than their proposed date, but these could still be 2030 onwards.
This issue has become such a frustration to investors and customers that the former Prime Minister, Rishi Sunak detailed changes needed to be made in his new approach to net zero speech given on the 20th September 2023.
Although there are encouraging noises being made by both National Grid and the Government, new connections will still be beyond most customers’ requirements for their own targets to reach net zero.
It is now more important than ever to ensure that grid applications are progressed as early as possible and that planning and funding is in place to ensure that “shovel ready” projects can connect to the grid as quickly as required and they are not sat in a queue awaiting a long connection date.
Additional mitigation measures can also be considered to overcome these timescales by ensuring that any proposed scheme does not significantly impact either the DNO's or Grid's existing network. Schemes such as Active Network Management, Curtailment schemes, export limitation, fault level reduction could be introduced into the design at an early stage, ensuring an early connection.
Communications should be started with the local Distribution Network Operator at the feasibility stage of the scheme. This will allow any potential limitations on the network to be known about in advance of a timely and costly application being submitted, and should also inform the size and design of the scheme. Early engagement with DNOs has enabled us to convert many schemes into real projects that might otherwise have been sat in a queue.
Many clients who wish to use renewable electricity generation as a way to decarbonise are now in a position where this is not viable within their set timeframe. If we scale this across the entire country, then it becomes a genuine barrier to the UK meeting its net zero targets.
Experienced energy partners, like Vital Energi, can help clients evolve their projects so that they are both technically and economically viable. All schemes are unique, so solutions need to be unique too, but by partnering with an experienced service provider, clients are able to access their considerable experience of finding creative solutions to unlock projects.
If you’d like to discuss your potential project and the options available to you then please get in touch with us.