"It is great to see work is starting next week on the new Torry Heat Network which will bring low-cost heat to tenants’ homes and public buildings. This will help people with fuel poverty and ensuring they have somewhere warm to live, as well as helping Aberdeen with the goal of reaching net zero for the city. We look forward to watching the work progress in the coming months."
As well as work to streets to install the more than 3.7 miles of underground pipes, the project also includes new internal installations, heat metering, and heat supply pipes to the interior of the buildings.
The main spine heat distribution pipes from the heat distribution facility are to be routed underneath the Aberdeen to Dundee railway line to connect with the existing heating network in Torry.
It is expected the work will finish late 2023, depending on weather and availability of materials world-wide.
The main contractor for the work is Vital Energi, which will be carrying out local stakeholder engagement, and appointed Barhale is the specialist design and build under track crossing contractor.
The project is to receive £5.787million of grant funding from the Scottish Government’s Low Carbon Infrastructure Transition Programme and the European Regional Development Fund.