Executive Summary

We continue our work on the Royal Warwick Square Development with the £6.8m mechanical and engineering contract on Phase 2 of the project.

  • stats-numerical
    £6.8m contract value
  • Pipes And Pipework

Project Overview

This is the third contract which we have won on the Kensington-based development and will us delivering essential infrastructure for Block J, creating 86 extra care dwellings which are owned by Goldman Sachs and operated by Riverstone.

Our Solution

Vital 21 7 007

We will progress the design from RIBA stage 3 RIBA stage 5 and deliver essential infrastructure including:

  • Nurse Call System
  • Orcomm home automation system with Concierge integration
  • WAP
  • Apartment fire suppression systems
  • Water Leak Detection within all Bathrooms, Kitchens and Mechanical Cupboards
  • Fire stopping solution in conjunction with Hilti
  • Viega Pipework including Smart press within Apartments
  • Rainwater Harvesting system for the site wide irrigation system
Solution detail