We are really excited by this project. It represents the first step in a network of low carbon energy projects, which will provide cleaner, greener, affordable and more secure energy supplies for communities across Camden.
Councillor Meri, Cabinet Member for Sustainability and EnvironmentThe project presented our designers with a challenge as they would be designing the initial stages of what will become one of London’s major heat networks. The location of the installation made the project extremely challenging. Located close to Euston Station and St. Pancras International Station, the area would involve removal and reinstatement of cobbles, working on busy highways and walkways, and dealing with the congested existing utilities in central London.
After extensive heat loss calculations and comparisons, we specified Logstor Series 3 single pipework which has an expected design life in excess of 50 years. The 581m of district heating pipe which makes up the core of Phase 1 will include a range of pipe sizes. After careful analysis of potential future heat loads, all have been sized to allow for planned future expansion and range from 65mm to 250mm pipework.
The pipework has a moisture detection alarm system installed, accurate to 1m, allowing any issues to be addressed as early as possible and before a leak occurs. In total, the Phase 1 district heating network will connect 339 properties, with 184 further properties connected in Phase 2, as well as the school and community centre.
The energy centre is in a former underground car park which has been retrofitted and has seen us employ a creative design to comply with the original building. This can be seen in the flue solution which was designed to run up the side of the building and has been clad to match the building’s other lift shaft.
Contingency was built into the design to accommodate future increased demand and also to ensure ease of expansion for future planned connections. For the first phase of the energy centre, three 1.3MWth boilers were installed with space left for further plant and equipment. The energy centre supplied heat and hot water for the first phase for two years before the second phase saw the installation of a 900kW CHP engine, four 9,000L thermal stores and three 11,000L thermal stores.
The delivery of the plant equipment for Phase 2 of the project was carried out over a two day period which saw us complete all traffic and pedestrian access management to ensure safety. We aimed to minimise disruption as much as possible by completing the deliveries on a weekend to alleviate traffic congestion.
Camden Council had given a great deal of thought to the possible long-term evolution of their heat network, and have procured a comprehensive 15 year Asset Management contract with Vital which will guarantee a minimum efficiency performance level in excess of 80% for the system.
The network has been designed so that after the CHP’s lifecycle expires, Camden will be able to use whatever the most low carbon and cost effective technology of the future may be.